Architecture Term

Building Permit

The official authorization required from the relevant municipality before construction can start. It's issued once the architectural, structural and MEP (mechanical/electrical/plumbing) designs have been coordinated and submitted together.

Also available in:Türkçe (Yapı Ruhsatı)·رخصة البناء

When a permit is mandatory

Under Article 21 of Turkey's Zoning Law, a building permit from the municipality or governorship is mandatory for all structures within the scope of the Law[1]. Any change to a permitted structure also requires a new permit. Work such as joint repair, plastering, painting, joinery, floor and ceiling finishes, electrical and plumbing repairs and roof repair does not need a permit[1].

What the application needs and how long it takes

Under Article 22, owners or their legal representatives apply by petition, attaching the title deed, architectural project, structural project, electrical and plumbing projects and calculations[1]. If the application and its attachments are complete and correct, the permit is issued within thirty days at most from the application date. If anything is missing or wrong, it is notified in writing within fifteen days, and the permit is issued within fifteen days at most after the application is resubmitted[1]. Before applying, the zoning status document is obtained (zoning status).

The building inspection contract

For the permit application a service contract with an authorised building inspection company must be signed[2]. For buildings up to 500 m² of construction area the owner chooses the company; for larger buildings the contract is made with one of at most two companies determined electronically[2]. For all the steps see our building permit checklist.

Frequently asked questions

When is a building permit needed?

Under Article 21 of the Zoning Law, a building permit is mandatory for all structures within the scope of the Law, and any change to a permitted structure also needs a new permit.

How long does a building permit take?

Under Article 22, if the application and its attachments are complete and correct, the permit is issued within thirty days at most from the application date. If something is missing, it is notified in writing within fifteen days.

Do painting and repairs need a permit?

No. Under Article 21, joint repair, plastering, painting, joinery, floor and ceiling finishes, electrical and plumbing repairs and roof repair do not need a permit.

Sources

  1. Zoning Law (İmar Kanunu, No. 3194), Articles 21 and 22 (permit requirement, application documents, time limits)
  2. Law on Building Inspection (No. 4708), Articles 2 and 5 (inspection and service contract)