Architecture Term

Soil Survey

A geotechnical report establishing a plot's soil-bearing characteristics (load capacity, borehole depth, soil class) that the structural design is built on. Under Turkey's Planned Areas Zoning Regulation, Article 57, the structural project must be prepared in line with this report; without it there is no structural project, and without a structural project no building permit.

Also available in:Türkçe (Zemin Etüdü)·دراسة التربة

What the report establishes

A soil survey is a technical report in which an authorised geology or geophysics engineering firm uses boreholes and laboratory tests on the plot to establish the soil's bearing capacity, layer structure, groundwater level and earthquake behaviour (soil class). The structural engineer chooses the foundation type (raft, pad, piled) and the structural calculations based on this report.

Two separate reports in the regulation

Under Turkey's Planned Areas Zoning Regulation, for new construction the application obtains from the authority the part of the approved geological and geotechnical report underlying the zoning plan that covers the parcel (Art. 55/2); the authority issues a copy together with the zoning status document within two working days at most (Art. 55/4)[1]. In addition, the structural project is prepared in line with the soil and foundation survey report made for the specific parcel (Art. 57)[1]. So the plan-level report and the borehole survey on your plot are not the same document.

Why it matters more on a slope

On sloping land the survey also reveals slope stability, possible slip risk and drainage; this information determines the level the building sits on and whether a retaining wall is needed. For details see our article on building on a sloped lot.

Frequently asked questions

Is a soil survey mandatory?

Yes. Under Article 57 of the Planned Areas Zoning Regulation the structural project is prepared in line with the soil and foundation survey report; without the report there is no structural project, and without that no building permit.

What does a soil survey report contain?

Bearing capacity, soil layers, groundwater level and earthquake behaviour (soil class), based on boreholes and laboratory tests.

Is a geological report issued with the zoning status document?

Under Article 55/4 the authority issues a copy of the approved geological and geotechnical report together with the zoning status document within two working days at most. This is the plan-level report; it does not replace the survey made for your own parcel.

Sources

  1. Planned Areas Zoning Regulation (Planlı Alanlar İmar Yönetmeliği), Articles 55/2, 55/4 and 57 (geological and geotechnical report, soil and foundation survey)